This work problem from Geoffrey Mott-Smith is a little bit tricky.
“An engineer working on the Alcan Highway was heard to say, “At the time I said I could finish this section in a week, I expected to get two more bulldozers for the job. If they had left me what machines I had, I’d have been only a day behind schedule. As it is, they’ve taken away all my machines but one, and I’ll be weeks behind schedule!”
How many weeks?”
See the Alcan Highway Problem for a solution.